Definition
It is used for any repairs on plaster surfaces, any concealing and filling processes, etc. in constructions. Area of application It is used for any concealing and filling processes, cast, suspended ceiling construction, marble bonding, etc. in constructions.
Application features
-Using period: 5-6 minutes -Setting Time: 15-16 minutes -It ensures that the basic filling and repair works are done quickly. -Its setting time is very short. Surface Preparation -The application surfaces must be cleared of dust, dirt, oil, etc. that prevent adherence. -The surface must be wet in dry and hot weather conditions. Application Conditions -Ambient temperature should be between +5°C and +35°C -Do not apply on frozen, melting surfaces, or surfaces likely to freeze within 24 hours. -Do not apply on surfaces under direct sun or strong wind, or hot surfaces. -The newly applied surfaces must be protected against water contact definitely. Warnings and Advices -Pay attention to the water/plaster ratio of the mix. Otherwise, it may cause spalling, cracks or strength reduction. -Do not apply in very hot, dry or windy environments. If applied in very hot environments, it may cause spalling, cracks and strength reduction consequently. -Pay attention to the product storing conditions. Do not keep the product in humid or very hot places. -In case any petrification is found out in the bag, do not use the product.
Definition
It is used for any repairs on plaster surfaces, any concealing and filling processes, etc. in constructions.
Area of application
It is used for any concealing and filling processes, cast, suspended ceiling construction, marble bonding, etc. in constructions.
Application features
-Using period: 5-6 minutes
-Setting Time: 15-16 minutes
-It ensures that the basic filling and repair works are done quickly.
-Its setting time is very short.
Surface Preparation
-The application surfaces must be cleared of dust, dirt, oil, etc. that prevent adherence. -The surface must be wet in dry and hot weather conditions.
Application Conditions
-Ambient temperature should be between +5°C and +35°C
-Do not apply on frozen, melting surfaces, or surfaces likely to freeze within 24 hours.
-Do not apply on surfaces under direct sun or strong wind, or hot surfaces.
-The newly applied surfaces must be protected against water contact definitely. Warnings and Advices
-Pay attention to the water/plaster ratio of the mix. Otherwise, it may cause spalling, cracks or strength reduction.
-Do not apply in very hot, dry or windy environments. If applied in very hot environments, it may cause spalling, cracks and strength reduction consequently.
-Pay attention to the product storing conditions. Do not keep the product in humid or very hot places.
-In case any petrification is found out in the bag, do not use the product.
-Do not breathe its powder since it consists of various chemical additives and
plaster. Avoid contact with skin and eyes. In case of contact, wash your skin/eyes with plenty of water. Use protective equipment such as mask, gloves etc. during the works. Application Tools
Hand mixer, trowel and steel trowel
Application
1. The container in which the mortar will be prepared must be clean and cleared of the
remnants of the previous mixture.
2. The water used in the mixture should not be salty, acidic or oily. The water temperature
must be between 17 and 23°C.
3. The mortar must be prepared by using 7 kg of water and 10 kg of BGC Gypsum Repair
Plaster.
4. Water is poured into the container, and then BGC Gypsum Repair Plaster is added. The
plaster is given 2-3 minutes to absorb the water.
5. The plaster is mixed until a homogeneous consistency is achieved by mixing with a
trowel or hand mixer. No other product or materials must be added to BGC Gypsum
Repair Plaster mixture.
6. No water or plaster should be added into the mortar during or after mixing.
7. It must be ensured that the application surface is moistened prior to application.
8. The mortar ready for the application is applied on the surface to be repaired or filled
using a spatula. When the plaster begins to set, the surface is smoothened using a
spatula.
Storage Conditions
Bags must be stored in a dry place and to a height that does not exceed 18 bags. Bags must be stored so as not to contact with the ground in order them to be protected against humid. BGC Gypsum Repair Plaster stored as described above must be used within 12 months as of the production date. Inappropriate storage or exceeding the expiry date may deteriorate the properties of the product.